Will acousticians conduct on-the-ground surveys in the actual Delta?
June 15, 2020Can we add to Map 8: historical sites, cultural resources and Indian burial grounds?
June 15, 2020The shaft construction process would require a large crane or milling machine for the slurry panel excavation or panel excavator if cutter soil mix panels were used. A second crane would be required to support operations for the panel construction (e.g., lifting the steel rebar reinforcing cages into the panel excavations). Based on current information, the loudest construction noise would generally be related to the motor noise from these two pieces of equipment.