What will be the impact of dewatering and excavation on aquifers?
June 12, 2020How many tons of concrete will be poured on the launch shaft site pads?
June 12, 2020We do not expect seepage from connecting tunnel segments due to the construction method. The tunnel segments are put together within the cylindrical steel shield of the TBM, and seepage is controlled by multiple wire brush seals as the segments are assembled together. The segments themselves are gasketed at all of the joints, essentially providing a completely sealed system.