The data in the presentation was shown for one launch, maintenance or reception shaft site. The launch shafts would be located approximately 15 miles from the reception shaft with maintenance shafts located approximately every 5 miles between the launch and reception shafts. Several tunnel boring machines could be operating at launch shafts simultaneously; however, the schedules have not been completed at this time.